Installation - Partition Wall Restraint

PWR

Installation

Installation
  • Position the connector on top of the header rail and against the floor joist.
  • Secure the connector to the header rail with the specified fasteners.
  • The bottom of the location tab should sit on the top of the header rail.
  • Secure the connector to the joist with the specified fasteners, allowing a 1-2mm gap between the underside of the fastener head and the PWR connector.
  • Maximum gap between the partition and the joist is 15mm.
  • Ensure that the fastener is at the upper edge of the tapered slot as this allows for the deflection of the joist.
  • 1. Floor Joist
2. 15mm gap between joist and header rail.
3. Header Rail of partition
4. 1-2mm gap between fastener head and connector.
5. Location Tab. - Partition Wall Restraint
    1. Floor Joist 2. 15mm gap between joist and header rail. 3. Header Rail of partition 4. 1-2mm gap between fastener head and connector. 5. Location Tab.