Technical Notes - Safety Fast Lite Hanger

SFLHI

Technical Notes

General Installation Notes
  • The floor decking may be stored on the joists provided the load is uniformly distributed between the several joists and does not exceed the hanger or joist capacities. Refer to joist manufacturer or supplier for joist capacity and maximum construction loads.
  • The floor decking must be securely attached to each joist before additional loads can be placed on the system.
  • Floor decking and block work is to be cut where necessary to fit around the upstand stiffeners.
  • Pallets of blocks or other construction materials should be placed onto the scaffolding and NOT directly onto the floor. The materials can then be evenly distributed around the floor manually, ensuring hanger or joist capacities are not exceeded.