Installation
  • Position the MJC’s onto the 1st joist - ensuring that they are centred about the incoming load at 400 c/c (may be adjusted within 10mm each way).
  • Please note that the connectors can be installed in any orientation. Secure each MJC with 4no. 3.75 x 30mm Square Twist Nails, to the top and bottom joist flanges as shown.
  • Position 2nd joist ensuring ends are flush and joists are parallel. Secure the joist using 2no. 3.75 x 30mm Square Twist Nails per MJC into the top and bottom joist flanges as shown.
  • Multiple Joist Connector
  • Multiple Joist Connector